Friday, 24 January 2014

Do Environmental Permitting and Planning Actions Have a Difficult Relationship?



The English High Court handed down a ruling that provided English planning authorities the right to deny planning permission in circumstances where they have grounds to contend that the environmental effects of a particular development project are not necessarily catered to by existing licensing or permitting regimes.
The nature of the relationship between environmental permitting and planning controls has been seen as unclear in legal spheres for years. The crux of the debate concerns the extent that the planning authority, acting to determine application, has to consider or implement conditions in line with environmental impacts in the instance these are to be regulated by a separate body under the auspices of a separate statutory regime.
In the Northern Irish legal cannon a measure of clarification to this question is brought via Planning Policy Statement (“PPS”) 11 – Planning and Waste Management. Here it is stated that planning control “should not duplicate other statutory controls” and that planning decisions should be made “on the basis that the pollution control regimes will be properly applied and enforced”. In theory the application of this provision is narrow; it applies to waste management. However in actuality this key point can be applied to the myriad of activities subject to environmental permitting. 

The case Harrison v Secretary of State for Communities and Local Government and Cheshire West and Chester Council ([2009] EWHC 3382) provides a further measure of clarification. The case involved an animal processing plant characterised by a lengthy history of complaints from the local populace due to the odour its activities released into the surrounding area. 

The facility itself did not have planning permission; however the local council did engage in regulating the site under the provisions of a Pollution Prevention and Control (“PPC”) Permit. A Planning Inspector was requested in to ascertain whether a deemed planning application should be allowed after a planning enforcement notice was served, which was appealed by the operators of the site. The Inspector considered English PPS 23, which reflects the principles of NI PPS 11, laid out above, when deciding to dismiss the appeal request and ultimately deny planning permission. In the decision the Inspector put forward the argument that the odour issues had a high chance of persistence in spite of the controls of the PPC Permit. The operator further appealed this decision based on the principle that the guidance put down in PPS 2 had been disregarded, with no justification for doing so having been stated. 

In its ruling the High Court stated that planning authorities should work on the basis of assurance that the environmental permitting regime will be correctly enforced and monitored. Despite this the judgements did not call on planners to categorically decide that no pollution issues would arise: “if the decision-maker considered that there might be adverse consequences... on amenity and/or issues as to the appropriateness of locating the development of the site in question... he was entitled to regard such matters as material considerations”.

The landmark Harrison judgement can be used to provide a greater degree of clarification on the role of planning authorities in deciding upon applications for development that fall under the auspices of environmental permitting. Considering the overarching similarity between the environmental permitting regimes in England and Northern Ireland, along with the planning guidance provided on this issue, this ruling can be directly applied to this jurisdiction. The principles gleaned from this judgement could be considered as applicable to other statutory controls such as waste management licences or water discharge consents in the eventuality that they hold relevance to a planning application. 

This ruling alludes to the idea that planning authorities should be allotted the right to an increased emphasis to likely environmental risks rather than taking these issues and delegating this consideration to the NI Environment Agency or local council as environmental regulator. However this argument carries the risk of flooding the planning authority with technical issues that should fall completely under the remit of the expert environmental regulators. Furthermore this ruling would seem to hold a greater significance for facilitates that have experienced environmental issues for a sustained period of time. In considering this issue in relation to new developments we come to the conclusion that it is a difficult task to pinpoint environmental risks that are not provided for under relevant permits and should naturally be taken into account by the planning authority. An issue as complex as this is destined to appear before the courts at some point in the future; in some ways the issue remains as unclear as ever. 

Should you have any questions on the topics discussed in this article or more general questions on environmental issues facing your business, please contact Andrew Ryan at Tughans on 028 9082 0527 or email andrew.ryan@tughans.com