Friday, 31 January 2014

A Provision for Greater Clarification on the Contaminated Land Regime

The operation of the statutory regime built to impose liability for historic contamination and pollution has received a greater degree of clarification due to the rulings of a case in the UK High Court; the case is the first of its kind. In England, Part 2a of the Environmental Protection Act 1990 (EPA) provides provisions for a statutory scheme purposed with the goal of determining which party is liable to paying the costs incurred in the cleaning up of contaminated land. The Waste and Contaminated Land (NI) Order 1997 lays out a highly similar scheme for this issue in the Northern Irish legal cannon. The NI scheme has yet to come take effect because it demands retrospective liability for historic contamination. However its implications need to be rigorously assessed in anticipation of when it will do so.

The English case in question concerns a remediation notice the Environment Agency served with regard to an area situated in St Leonard’s Court, which lies close to Hatfield. The site in question is a residential estate in the present day, however it was formerly a chemical works facility and consequently it stands above a large area of ground water contamination. This ground water contamination resulted in the closure of a whole roster of public water facilities as well as the imposition of restrictions on the use of some others in an area twenty kilometres clear of the site. Redland Minerals Limited held possession of the site in the early 1980’s. It sold the site to Crest Nicholson Residential plc. who were responsible for developing the site. A Key fact to note is that Crest Nicholson was informed of the nature of contamination of the site prior to purchase. This knowledge was provided both by Redland itself and as a consequence of inquiries made to the local council in the same period. The contamination wrought on the site, caused by Bromate and Bromide, two toxic chemicals, was a fact that Crest was aware of; consequently the degree of contamination was heightened due to demolition of parts of the site, as this allowed rainwater to aid the substances permeation of ground water.
Under part 2a of the EPA a remediation notice was served in 2005 that determined that both Redland and Crest were liable for covering the significant remediation costs. This notice underwent appeal from both applicable parties which consequently saw the Secretary of State appoint an Inspector who dismissed the appeal once the major investigation into the issue reached its conclusion. Accordingly this dismissal by the Secretary of State was submitted for judicial review by Redland and Crest. Mr. Justice Sales decided to dismiss the application for judicial review in February 2010, in the process validating the primary decision of the inspector.

A key issue that both the Inspector and the High Court deliberated upon was Redlands scope for liability under the case. According to Part 2a, a statutory exclusion from liability is applicable in situations where the seller of a contaminated site has “sold with information”. In its most broad definition, this provision allows the seller of the site to be excluded from the provision of any future liability in situations where said seller provides the purchaser with information on the nature and scope of the site contamination or permits the purchaser to mount an investigation of its own into contamination of a site. In this instance complete liability then falls onto the purchaser of the site. Inserting “sold with information” clauses with the intention of transferring liability to purchasers or tenants on long lease of sites has evolved to become standard practice in the property transactions of contaminated or potentially contaminated land. The application of the “sold with information”  clause led all adjudicators to conclude that Redlands held partial liability in the case due to the fact that Crest were only made partially aware of  the extent of ground water contamination when the purchase was conducted. Both the information available and that ascertained from Crest’s own investigations only established the Bromide contamination. Additionally Crest was tasked to also take partial responsibility for the leakage of Bromide into the ground water due to their demolishing of the site in question. This facilitated the infiltration of Bromide via rain water.

These landmark rulings lead Tughans to the conclusion that the effectiveness of the “sold with information” clause needs to be reevaluated. The actuality of the exclusion may be circumstantial. It may depend upon factors such as the factual circumstances of the transaction in question, the breadth of knowledge and disclosure by the parties and what said parties may reasonably be expected to become aware of. Although the St Leonard’s Court case is one of extremity, it establishes legal principles which must be taken into evaluation both in future transactions and maybe in those where the “sold with information” exclusion has traditionally been relied upon.

Should you have any questions on the topics discussed in this article or more general questions on environmental issues facing your business, please contact Andrew Ryan at Tughans on 028 9082 0527 or email andrew.ryan@tughans.com

Friday, 24 January 2014

Do Environmental Permitting and Planning Actions Have a Difficult Relationship?



The English High Court handed down a ruling that provided English planning authorities the right to deny planning permission in circumstances where they have grounds to contend that the environmental effects of a particular development project are not necessarily catered to by existing licensing or permitting regimes.
The nature of the relationship between environmental permitting and planning controls has been seen as unclear in legal spheres for years. The crux of the debate concerns the extent that the planning authority, acting to determine application, has to consider or implement conditions in line with environmental impacts in the instance these are to be regulated by a separate body under the auspices of a separate statutory regime.
In the Northern Irish legal cannon a measure of clarification to this question is brought via Planning Policy Statement (“PPS”) 11 – Planning and Waste Management. Here it is stated that planning control “should not duplicate other statutory controls” and that planning decisions should be made “on the basis that the pollution control regimes will be properly applied and enforced”. In theory the application of this provision is narrow; it applies to waste management. However in actuality this key point can be applied to the myriad of activities subject to environmental permitting. 

The case Harrison v Secretary of State for Communities and Local Government and Cheshire West and Chester Council ([2009] EWHC 3382) provides a further measure of clarification. The case involved an animal processing plant characterised by a lengthy history of complaints from the local populace due to the odour its activities released into the surrounding area. 

The facility itself did not have planning permission; however the local council did engage in regulating the site under the provisions of a Pollution Prevention and Control (“PPC”) Permit. A Planning Inspector was requested in to ascertain whether a deemed planning application should be allowed after a planning enforcement notice was served, which was appealed by the operators of the site. The Inspector considered English PPS 23, which reflects the principles of NI PPS 11, laid out above, when deciding to dismiss the appeal request and ultimately deny planning permission. In the decision the Inspector put forward the argument that the odour issues had a high chance of persistence in spite of the controls of the PPC Permit. The operator further appealed this decision based on the principle that the guidance put down in PPS 2 had been disregarded, with no justification for doing so having been stated. 

In its ruling the High Court stated that planning authorities should work on the basis of assurance that the environmental permitting regime will be correctly enforced and monitored. Despite this the judgements did not call on planners to categorically decide that no pollution issues would arise: “if the decision-maker considered that there might be adverse consequences... on amenity and/or issues as to the appropriateness of locating the development of the site in question... he was entitled to regard such matters as material considerations”.

The landmark Harrison judgement can be used to provide a greater degree of clarification on the role of planning authorities in deciding upon applications for development that fall under the auspices of environmental permitting. Considering the overarching similarity between the environmental permitting regimes in England and Northern Ireland, along with the planning guidance provided on this issue, this ruling can be directly applied to this jurisdiction. The principles gleaned from this judgement could be considered as applicable to other statutory controls such as waste management licences or water discharge consents in the eventuality that they hold relevance to a planning application. 

This ruling alludes to the idea that planning authorities should be allotted the right to an increased emphasis to likely environmental risks rather than taking these issues and delegating this consideration to the NI Environment Agency or local council as environmental regulator. However this argument carries the risk of flooding the planning authority with technical issues that should fall completely under the remit of the expert environmental regulators. Furthermore this ruling would seem to hold a greater significance for facilitates that have experienced environmental issues for a sustained period of time. In considering this issue in relation to new developments we come to the conclusion that it is a difficult task to pinpoint environmental risks that are not provided for under relevant permits and should naturally be taken into account by the planning authority. An issue as complex as this is destined to appear before the courts at some point in the future; in some ways the issue remains as unclear as ever. 

Should you have any questions on the topics discussed in this article or more general questions on environmental issues facing your business, please contact Andrew Ryan at Tughans on 028 9082 0527 or email andrew.ryan@tughans.com